Another landslip - Knottingley (Pontefract East area)

johntea

Established Member
Joined
29 Dec 2010
Messages
2,610
Yvette Cooper has been piping up recently moaning the works are taking too long and 'letting the North down' :D

Although from what I've seen the replacement buses have been running like clockwork and I was particularly impressed with one operator who seems to have managed to convert the Northern logo into a digital format for their destination display screen!
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

1D53

Established Member
Joined
2 Apr 2006
Messages
2,710
Looks like reopening on the 29th as good progress has been made.
 

Class158North

New Member
Joined
3 Apr 2023
Messages
4
Location
Featherstone, West Yorkshire
Line now confirmed to be reopen with services from Leeds via Wakefield running to Knottingley again from Monday 29th April.

Services from Leeds via Castleford will start running to Knottingley from Saturday 4th May with rail replacements continuing until then.

Some progress on Knottingley trains. Network Rail has said the landslip is now repaired. Northern Rail says it is restarting services.
Train services from Wakefield & Pontefract to Knottingley will restart on Monday, April 29th

Trains from Castleford to Knottingley will restart on Saturday, May 4th (with continued rail replacement buses until then).

I’m glad the work is now complete after we called on them to make it a priority. Knottingley needs its train service back.
 
Last edited by a moderator:
Joined
26 May 2023
Messages
7
Location
Leeds
Is there a speed restriction in place hence the Leeds - Knottingleys (via Castleford) still terminating at Cas for now?
 

Adam0984

Member
Joined
18 Feb 2014
Messages
1,078
Is there a speed restriction in place hence the Leeds - Knottingleys (via Castleford) still terminating at Cas for now?
It's because the crew diagrams can't be changed at such a late hour. The via Wakefields have 40 mins at Pontefract at the moment so will just carry on to Knottingley for 30 mins, where as the Castleford ones just shuttle back and forth with 15 mins at Castleford
 

1D53

Established Member
Joined
2 Apr 2006
Messages
2,710
Correct. NWR advice was too late.
It's because the crew diagrams can't be changed at such a late hour. The via Wakefields have 40 mins at Pontefract at the moment so will just carry on to Knottingley for 30 mins, where as the Castleford ones just shuttle back and forth with 15 mins at Castleford
 

snowball

Established Member
Joined
4 Mar 2013
Messages
7,763
Location
Leeds
Press release


Rail passengers in Knottingley are being thanked by Network Rail for their patience and understanding during recent disruption to train services as work is completed to repair a landslip in the area.

The line between Knottingley and Pontefract Monkhill has reopened this morning following seven weeks of round-the-clock work by Network Rail engineers to rebuild an embankment after it slipped in early-March.

More than 2,000 tonnes of stone has been installed along with a new 30m retaining wall structure to strengthen the land. 60 metres of track has been removed and replaced, with engineers also carrying out signalling and telecommunications work.

Teams have been working around the clock to reopen the line for local communities, with Network Rail thanking passengers and residents for their patience and understanding while the work has been carried out.

The landslip is believed to have been caused by the recent prolonged period of wet weather. However, during investigations, minor voids were discovered beneath the railway embankment that are believed to relate to historic mineral mining in the area. This has meant that the work to reopen the line has taken longer and has been more complex to complete.

Extensive work has since been carried out to fill the voids while engineers have also worked to reinstate the railway infrastructure above to allow the line to be reopened.

Engineers will continue to monitor the embankment to make sure that the land remains safe for trains to run over, with a temporary speed restriction in place through the area.

A rail replacement service has operated by Northern throughout the closure to keep passengers connected.

Over the next five years, Network Rail is investing £60m in Yorkshire and the North East to help tackle disruption brought by severe weather, with major drainage schemes taking place throughout the region and the creation of new dedicated drainage roles on the organisation’s North & East route.
 