It's always hard to judge that one, but it's more likely now they are in capped cost mode.Not bad - presumably there was a pause or at least slowdown over Easter?
No update from the other TBMs, and "Elizabeth" is not yet even on the map at Bromford despite starting a month ago (March 5).
"Anne" was supposed to start at Victoria Road in "March" too, but there's been no announcement.
Edit Apr 8:
The Northolt East TBMs have been updated today.
Emily is still at 176m (not moved since March 25).
Anne has its first report at 15m, after being launched in "March", and its graphic is now on the map.
If the graphics are in the right position, Emily is boring the south/west bore (ie the Down tunnel), and Anne is boring the north/east tunnel (the Up tunnel).
Ignoring the Euston tunnels, all the Phase 1 TBMs are now operational, though we still need a first position for Elizabeth at Bromford.